Peter Green Chilled

Peter Green Chilled: High Capacity Chilled Storage Upgrade

Shepton Mallet, UK

Pallet Racking

Peter Green Chilled

Peter Green Chilled: High Capacity Chilled Storage Upgrade

Shepton Mallet, UK

Pallet Racking

Peter Green Chilled

Peter Green Chilled: High Capacity Chilled Storage Upgrade

Shepton Mallet, UK

Pallet Racking

Project Overview

Two pallet types. One adaptable system. More capacity in the cold.

When Peter Green Chilled needed to replace its existing pallet racking, the project required careful planning to accommodate the demands of a chilled environment and a fully operational warehouse.

Used Racking UK dismantled the existing system and installed new Mecalux adjustable pallet racking, designed to accommodate different pallet types and load requirements. The existing wire guidance system was also altered to suit the revised layout.

Completed over four planned visits, the installation created a flexible storage solution capable of holding 1,040 UK pallets and 900 Euro pallets, while allowing the business to maintain its day to day operations.

The Solution

Used Racking UK planned the replacement around Peter Green Chilled's operational requirements, dividing the work across four visits to minimise disruption and keep the project moving.

During the first visit, all racking frames were assembled during normal working hours. The remaining work was then carried out over three weekend visits, with two rows of racking replaced during the first weekend and the associated wire guidance alterations completed alongside the installation.

The following two visits involved replacing further racking runs and adapting the wire guidance system to accommodate the new layout. During the final visit, the remaining racking was installed and the anti-collapse mesh fitted.

The new Mecalux adjustable pallet racking system accommodates both UK and Euro pallets, with maximum pallet loads of 1,200kg and frame heights reaching approximately 8m. A combination of 2.225m and 2.7m beam lengths allows the layout to make effective use of the available warehouse space.

The installation also included a dedicated anti-collapse mesh run measuring over 41.7m long and 7.8m high, providing additional protection within the storage environment.

The solution included:

  • Capacity for 1,040 UK pallets and 900 Euro pallets

  • New Mecalux adjustable pallet racking

  • Frame heights of up to 8,005mm

  • 2,225mm and 2,700mm beam lengths

  • Maximum pallet load of 1,200kg

  • Alterations to the existing wire guidance system

  • Anti-collapse mesh measuring over 41.7m long and 7.8m high

  • Installation planned across four visits to accommodate warehouse operations

The Result

The completed installation provided Peter Green Chilled with a new, high capacity storage system designed around its operational requirements.

By combining UK and Euro pallet compatibility with a revised layout and adapted wire guidance, the project delivered a flexible storage solution that makes effective use of the available space.

Careful scheduling allowed the work to be completed across four visits, with the main replacement work undertaken at weekends to minimise disruption to the warehouse operation.

The result was a complete storage upgrade, with the existing racking replaced, the wire guidance system adapted and anti-collapse mesh installed.

More capacity. Smarter use of space. Delivered around the operation.

Client Testimonial

“I cannot thank Pauline, Steve and the team enough.

Replacing the racking in a fully operational warehouse was always going to be a challenge so PG worked in conjunction with Pauline's team to divide the task across 4 weekends.

With all parties working together the task was completed on time with zero impact to service.

This project is testament to why Pauline has been our ‘go to’ partner for racking for the last 10 years.”

Malcolm Gold

General Manager

Peter Green Chilled

Project Overview

Two pallet types. One adaptable system. More capacity in the cold.

When Peter Green Chilled needed to replace its existing pallet racking, the project required careful planning to accommodate the demands of a chilled environment and a fully operational warehouse.

Used Racking UK dismantled the existing system and installed new Mecalux adjustable pallet racking, designed to accommodate different pallet types and load requirements. The existing wire guidance system was also altered to suit the revised layout.

Completed over four planned visits, the installation created a flexible storage solution capable of holding 1,040 UK pallets and 900 Euro pallets, while allowing the business to maintain its day to day operations.

The Solution

Used Racking UK planned the replacement around Peter Green Chilled's operational requirements, dividing the work across four visits to minimise disruption and keep the project moving.

During the first visit, all racking frames were assembled during normal working hours. The remaining work was then carried out over three weekend visits, with two rows of racking replaced during the first weekend and the associated wire guidance alterations completed alongside the installation.

The following two visits involved replacing further racking runs and adapting the wire guidance system to accommodate the new layout. During the final visit, the remaining racking was installed and the anti-collapse mesh fitted.

The new Mecalux adjustable pallet racking system accommodates both UK and Euro pallets, with maximum pallet loads of 1,200kg and frame heights reaching approximately 8m. A combination of 2.225m and 2.7m beam lengths allows the layout to make effective use of the available warehouse space.

The installation also included a dedicated anti-collapse mesh run measuring over 41.7m long and 7.8m high, providing additional protection within the storage environment.

The solution included:

  • Capacity for 1,040 UK pallets and 900 Euro pallets

  • New Mecalux adjustable pallet racking

  • Frame heights of up to 8,005mm

  • 2,225mm and 2,700mm beam lengths

  • Maximum pallet load of 1,200kg

  • Alterations to the existing wire guidance system

  • Anti-collapse mesh measuring over 41.7m long and 7.8m high

  • Installation planned across four visits to accommodate warehouse operations

The Result

The completed installation provided Peter Green Chilled with a new, high capacity storage system designed around its operational requirements.

By combining UK and Euro pallet compatibility with a revised layout and adapted wire guidance, the project delivered a flexible storage solution that makes effective use of the available space.

Careful scheduling allowed the work to be completed across four visits, with the main replacement work undertaken at weekends to minimise disruption to the warehouse operation.

The result was a complete storage upgrade, with the existing racking replaced, the wire guidance system adapted and anti-collapse mesh installed.

More capacity. Smarter use of space. Delivered around the operation.

Client Testimonial

“I cannot thank Pauline, Steve and the team enough.

Replacing the racking in a fully operational warehouse was always going to be a challenge so PG worked in conjunction with Pauline's team to divide the task across 4 weekends.

With all parties working together the task was completed on time with zero impact to service.

This project is testament to why Pauline has been our ‘go to’ partner for racking for the last 10 years.”

Malcolm Gold

General Manager

Peter Green Chilled

Project Overview

Two pallet types. One adaptable system. More capacity in the cold.

When Peter Green Chilled needed to replace its existing pallet racking, the project required careful planning to accommodate the demands of a chilled environment and a fully operational warehouse.

Used Racking UK dismantled the existing system and installed new Mecalux adjustable pallet racking, designed to accommodate different pallet types and load requirements. The existing wire guidance system was also altered to suit the revised layout.

Completed over four planned visits, the installation created a flexible storage solution capable of holding 1,040 UK pallets and 900 Euro pallets, while allowing the business to maintain its day to day operations.

The Solution

Used Racking UK planned the replacement around Peter Green Chilled's operational requirements, dividing the work across four visits to minimise disruption and keep the project moving.

During the first visit, all racking frames were assembled during normal working hours. The remaining work was then carried out over three weekend visits, with two rows of racking replaced during the first weekend and the associated wire guidance alterations completed alongside the installation.

The following two visits involved replacing further racking runs and adapting the wire guidance system to accommodate the new layout. During the final visit, the remaining racking was installed and the anti-collapse mesh fitted.

The new Mecalux adjustable pallet racking system accommodates both UK and Euro pallets, with maximum pallet loads of 1,200kg and frame heights reaching approximately 8m. A combination of 2.225m and 2.7m beam lengths allows the layout to make effective use of the available warehouse space.

The installation also included a dedicated anti-collapse mesh run measuring over 41.7m long and 7.8m high, providing additional protection within the storage environment.

The solution included:

  • Capacity for 1,040 UK pallets and 900 Euro pallets

  • New Mecalux adjustable pallet racking

  • Frame heights of up to 8,005mm

  • 2,225mm and 2,700mm beam lengths

  • Maximum pallet load of 1,200kg

  • Alterations to the existing wire guidance system

  • Anti-collapse mesh measuring over 41.7m long and 7.8m high

  • Installation planned across four visits to accommodate warehouse operations

The Result

The completed installation provided Peter Green Chilled with a new, high capacity storage system designed around its operational requirements.

By combining UK and Euro pallet compatibility with a revised layout and adapted wire guidance, the project delivered a flexible storage solution that makes effective use of the available space.

Careful scheduling allowed the work to be completed across four visits, with the main replacement work undertaken at weekends to minimise disruption to the warehouse operation.

The result was a complete storage upgrade, with the existing racking replaced, the wire guidance system adapted and anti-collapse mesh installed.

More capacity. Smarter use of space. Delivered around the operation.

Client Testimonial

“I cannot thank Pauline, Steve and the team enough.

Replacing the racking in a fully operational warehouse was always going to be a challenge so PG worked in conjunction with Pauline's team to divide the task across 4 weekends.

With all parties working together the task was completed on time with zero impact to service.

This project is testament to why Pauline has been our ‘go to’ partner for racking for the last 10 years.”

Malcolm Gold

General Manager

Peter Green Chilled

Get a Quote for Quality Used Racking Today

Maximise your warehouse space with quality used racking at unbeatable prices. Whether you need pallet racking, cantilever racking, or mezzanine flooring, we have cost-effective solutions ready for fast UK-wide delivery. Our team is here to help you find the perfect fit for your storage needs.

Why Get a Quote from Used Racking UK?


  • Save Money – Get quality used racking that is significantly cheaper and has the same safe quality.

  • Expert Guidance – Our team helps you find the right storage solution for your needs.

  • Fast UK-Wide Installation – Quick and reliable installation to your location.

  • Stock Availability – A wide range of used pallet racking and racking safety accessories are ready to go.

Tell us your requirements, and we’ll provide a competitive quote with expert advice. Fill out the form, and our team will be in touch quickly.

Get a Quote for Quality Used Racking Today

Maximise your warehouse space with quality used racking at unbeatable prices. Whether you need pallet racking, cantilever racking, or mezzanine flooring, we have cost-effective solutions ready for fast UK-wide delivery. Our team is here to help you find the perfect fit for your storage needs.

Why Get a Quote from Used Racking UK?


  • Save Money – Get quality used racking that is significantly cheaper and has the same safe quality.

  • Expert Guidance – Our team helps you find the right storage solution for your needs.

  • Fast UK-Wide Installation – Quick and reliable installation to your location.

  • Stock Availability – A wide range of used pallet racking and racking safety accessories are ready to go.

Tell us your requirements, and we’ll provide a competitive quote with expert advice. Fill out the form, and our team will be in touch quickly.

Get a Quote for Quality Used Racking Today

Maximise your warehouse space with quality used racking at unbeatable prices. Whether you need pallet racking, cantilever racking, or mezzanine flooring, we have cost-effective solutions ready for fast UK-wide delivery. Our team is here to help you find the perfect fit for your storage needs.

Why Get a Quote from Used Racking UK?


  • Save Money – Get quality used racking that is significantly cheaper and has the same safe quality.

  • Expert Guidance – Our team helps you find the right storage solution for your needs.

  • Fast UK-Wide Installation – Quick and reliable installation to your location.

  • Stock Availability – A wide range of used pallet racking and racking safety accessories are ready to go.

Tell us your requirements, and we’ll provide a competitive quote with expert advice. Fill out the form, and our team will be in touch quickly.

Get a Quote for Quality Used Racking Today

Maximise your warehouse space with quality used racking at unbeatable prices. Whether you need pallet racking, cantilever racking, or mezzanine flooring, we have cost-effective solutions ready for fast UK-wide delivery. Our team is here to help you find the perfect fit for your storage needs.

Why Get a Quote from Used Racking UK?


  • Save Money – Get quality used racking that is significantly cheaper and has the same safe quality.

  • Expert Guidance – Our team helps you find the right storage solution for your needs.

  • Fast UK-Wide Installation – Quick and reliable installation to your location.

  • Stock Availability – A wide range of used pallet racking and racking safety accessories are ready to go.

Tell us your requirements, and we’ll provide a competitive quote with expert advice. Fill out the form, and our team will be in touch quickly.